A dummy activity
A. Is artificially introduced
B. Is represented by a dotted line
C. Does not require any time
D. All of the above
Answer: Option D
Solution(By Examveda Team)
A dummy activity is a simulated activity of sorts, one that is of a zero duration and is created for the sole purpose of demonstrating a specific relationship and path of action on the arrow diagramming method.Related Questions on Industrial Engineering and Production Management