A having contracted with B to supply B with 1000 tons of iron at 100 Rs. a ton, to be delivered at a stated time, contracts with C for the purchase of 1000 tons of iron at 80 Rs. a ton, telling C that he requires so for the purpose of performing his contract in B. C fails to perform, A will be entitled to

A. Loss with he suffered @ Rs. 20 per ton

B. No compensation

C. Compensation for loss of profit alongwith any damages which he might have to pay to B on account of breach

D. None of the above

Answer: Option C


This Question Belongs to Law >> Indian Contract Act