A having contracted with B to supply B with 1000 tons of iron at 100 Rs. a ton, to be delivered at a stated time, contracts with C for the purchase of 1000 tons of iron at 80 Rs. a ton, telling C that he requires so for the purpose of performing his contract in B. C fails to perform, A will be entitled to
A. Loss with he suffered @ Rs. 20 per ton
B. No compensation
C. Compensation for loss of profit alongwith any damages which he might have to pay to B on account of breach
D. None of the above
Answer: Option C