A job can be done by 3 skilled workmen in 20 days or by 5 boys in 30 days. How many days will they take if they work together ?
Answer & Solution
Correct Answer:
Option
D
$$\eqalign{
& {\text{3 men's 1 day's work}} = \frac{1}{{20}} \cr
& {\text{5 boy's 1 day's work}} = \frac{1}{{30}} \cr
& \left( {{\text{3 men}} + {\text{5 boy}}} \right){\text{'s 1 day's work}} \cr
& = \left( {\frac{1}{{20}} + \frac{1}{{30}}} \right) \cr
& = \frac{5}{{60}} \cr
& = \frac{1}{{12}} \cr} $$
∴ 3 men and 5 boys will complete the work in 12 days.
∴ 3 men and 5 boys will complete the work in 12 days.