ExamVeda
Login
Home
11
A, B and C completed a work costing Rs. 1800. A worked for 6 days, B for 4 days and C for 9 days. If their daily wages are in the ratio of 5 : 6 : 4, how much amount will be received by A ?
Discuss
Answer & Solution
Answer: Option A
Solution:
Let the daily wages of A, B and C be Rs. 5x, Rs. 6x and Rs. 4x respectively.
Then, ratio of their amounts
$$\eqalign{ & = \left( {5x \times 6} \right):\left( {6x \times 4} \right):\left( {4x:9} \right) \cr & = 30:24:36 \cr & = 5:4:6 \cr & \therefore {\text{A's amount}} \cr & = {\text{Rs}}{\text{.}}\left( {1800 \times \frac{5}{{15}}} \right) \cr & = {\text{Rs}}{\text{.600}} \cr} $$
12
P and Q together can do a job in 6 days. Q and R can finish the same job in $$\frac{{60}}{7}$$ days. P started the work and worked for 3 days. Q and R continued for 6 days to finish the work. Then the difference of days in which R and P can complete the alone is P can complete the job alone is ?
Discuss
Answer & Solution
Answer: Option A
Solution:
L.C.M. of Total Work = 60
One day work of P + Q = $$\frac{{60}}{{6}}$$ = 10 unit/day efficiency
One day work of Q + R = $$\frac{{60}}{{\frac{{60}}{7}}}$$ = 7 unit/day efficiency
$$\eqalign{ & \left( {{\text{Q}} + {\text{R}}} \right){\text{ 6 days work}} \cr & = 7 \times 6 \cr & = 42{\text{ units}} \cr} $$
Then in 3 days = total work = 18
$$\eqalign{ & {\text{P completes}} \cr & = 60 - 42 \cr & = 18{\text{ units}} \cr & {\text{P's efficiency}} \cr & = \frac{{18}}{3} \cr & = 6{\text{ units/day}} \cr & {\text{Q's efficiency}} \cr & = 10 - 6 \cr & = 4{\text{ units/day}} \cr & {\text{R's efficiency}} \cr & = 7 - 4 \cr & = 3{\text{ units/day}} \cr & {\text{P completes whole work in}} \cr & = \frac{{60}}{6} \cr & = {\text{10 days}} \cr & {\text{R completes whole work in}} \cr & = \frac{{60}}{3} \cr & = {\text{20 days}} \cr & {\text{Difference is}} \cr & = \left( {20 - 10} \right) \cr & = 10{\text{ days }} \cr} $$
13
If the expenditure of gas on burning 6 burners for 6 hours a day for 8 days is Rs. 450, then how many burners can be used for 10 days at 5 hours a day for Rs. 625 ?
Discuss
Answer & Solution
Answer: Option D
Solution:
Shortest method of doing this question is ,
$${\text{Put in }}\frac{{{{\text{M}}_1} \times {{\text{T}}_1} \times {{\text{D}}_1}}}{{{{\text{W}}_1}}}$$     = $$\frac{{{{\text{M}}_2} \times {{\text{T}}_2} \times {{\text{D}}_2}}}{{{{\text{W}}_2}}}$$
$$\eqalign{ & {\text{Formula}} \cr & {\text{So, }} \cr & {\text{Let number of burners}} \to {\text{B}} \cr & \frac{{{\text{6B}} \times {6_{{\text{hours}}}} \times {8_{{\text{days}}}}}}{{450}} = \frac{{{\text{B}} \times 10 \times 5}}{{625}} \cr & {\text{After solving }} \to {\text{B}} = 8 \cr} $$
14
X can do a piece of work in 24 days. When he had worked for 4 days, Y joined him. If complete work was finished in 16 days, Y can alone finish that work in ?
Discuss
Answer & Solution
Answer: Option B
Solution:
Time and Work mcq solution image
$$\eqalign{ & {\text{According to the question,}} \cr & {\text{X}} \to {\text{24 days}} \cr & \Rightarrow {\text{Work done X in 4 days alone}} \cr & = 4 \times 1 \cr & = 4{\text{ units}} \cr & \Rightarrow {\text{Remaining work}} \cr & = 24 - 4 = 20{\text{ units}} \cr & \Rightarrow {\text{20 units done by both together in}} \cr & = \left( {16 - 4{\text{ days}}} \right) \cr & = 12{\text{ days}} \cr & {\text{Then efficiencies of }}\left( {{\text{X}} + {\text{Y}}} \right) \cr & = \frac{{{\text{Work}}}}{{{\text{Days}}}} \cr & = \frac{{20}}{{12}} \cr & = \frac{5}{3} \cr & = 1 + \frac{2}{3} \cr & \Rightarrow {\text{Efficiency of Y}} = \frac{2}{3} \cr} $$
Time taken by Y alone to complete the total work
$$\eqalign{ & = \frac{{24}}{{\frac{2}{3}}} \cr & = 36{\text{ days}} \cr} $$

Alternate :
$$\eqalign{ & {\text{X}} \times {\text{20}} = \left( {{\text{X}} + {\text{Y}}} \right) \times {\text{12}} \cr & \frac{{\text{X}}}{{{\text{X + Y}}}} \cr & = \frac{{12}}{{15}} \cr & = \frac{{3 \to {\text{Efficiency of X}}}}{{5 \to {\text{Efficiency of }}\left( {{\text{X}} + {\text{Y}}} \right)}} \cr & {\text{Efficiency of Y}} \cr & = 5 - 3 \cr & = 2{\text{units/day}} \cr & {\text{Total work}} \cr & = 24 \times 3 \cr & = 72{\text{units}} \cr & {\text{Total time taken by Y}} \cr & = \frac{{72}}{2} \cr & = {\text{36 days}} \cr} $$
15
Working efficiencies of P and Q for completing a piece of working are in the ratio 3 : 4. The number of days to be taken by them to complete the work will be in the ratio ?
Discuss
Answer & Solution
Answer: Option D
Solution:
Since we know efficiency and time are inversely proportion to each other.
$$\eqalign{ & \,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,{\text{P}}:{\text{Q}} \cr & {\text{Efficiency}}\,\,\,3:4 \cr & {\text{Time}}\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,4:3 \cr} $$
16
A and B can complete a piece of work in 12 and 18 days respectively. A begins to do the work and they work alternatively one at a time for one day each. The whole work will be completed in ?
Discuss
Answer & Solution
Answer: Option A
Solution:
$$\eqalign{ & \left( {{\text{A}} + {\text{B}}} \right){\text{'s 2 days work}} \cr & = \left( {\frac{1}{{12}} + \frac{1}{{18}}} \right) \cr & = \frac{5}{{36}} \cr & {\text{Work done in 7 pairs of days}} \cr & = \left( {\frac{5}{{36}} \times 7} \right) \cr & = \frac{{35}}{{36}} \cr & {\text{Remaining work}} \cr & = \left( {1 - \frac{{35}}{{36}}} \right) \cr & = \frac{1}{{36}} \cr & {\text{On 15th day, it is A's turn}}{\text{.}} \cr & \frac{1}{{12}}{\text{ work is done by A in 1 day}}{\text{.}} \cr & \frac{1}{{36}}{\text{ work is done by A in}} \cr & = \left( {12 \times \frac{1}{{36}}} \right) \cr & = \frac{1}{3}{\text{ day}}{\text{.}} \cr & \therefore {\text{Total time taken}} = 14\frac{1}{3}{\text{ days}} \cr} $$
17
A can do a piece of work in 90 days, B in 40 days and C in 12 days. They work for a day each in turn i.e., first day A does it alone, B does it the second day and C the third day. After that A does it for another day, and so on. After finishing the work they get Rs. 240. If the wages are divided in proportion to the work done by them, find what each will get ?
Discuss
Answer & Solution
Answer: Option A
Solution:
$$\eqalign{ & \left( {{\text{A}} + {\text{B}} + {\text{C}}} \right){\text{'s 3 days work}} \cr & = \frac{1}{{90}} + \frac{1}{{40}} + \frac{1}{{12}} \cr & = \frac{{43}}{{360}} \cr & \left( {{\text{A}} + {\text{B}} + {\text{C}}} \right){\text{'s 24 days work}} \cr & = \frac{{43}}{{360}} \times 8 \cr & = \frac{{344}}{{360}} \cr & {\text{Remaining work}} \cr & = \left( {1 - \frac{{344}}{{360}}} \right) \cr & = \frac{{16}}{{360}} \cr & = \frac{4}{{90}} \cr & {\text{On 25th day, it is A's turn}}{\text{.}} \cr & {\text{A's 1 day's work}} = \frac{1}{{90}} \cr & {\text{Remaining work}} \cr & = \left( {\frac{4}{{90}} - \frac{1}{{90}}} \right) \cr & = \frac{3}{{90}} \cr & = \frac{1}{{30}} \cr & {\text{On 26th day, it is B's turn}}{\text{.}} \cr & {\text{B's 1 day's work}} = \frac{1}{{40}} \cr & {\text{Remaining work}} \cr & = \left( {\frac{1}{{30}} - \frac{1}{{40}}} \right) \cr & = \frac{1}{{120}} \cr & {\text{On 27th day, it is C's turn}}{\text{.}} \cr & \frac{1}{{12}}{\text{ work is done by C in 1 day}}{\text{.}} \cr & \frac{1}{{120}}{\text{ work is done by C in }} \cr & = \left( {12 \times \frac{1}{{120}}} \right) \cr & = \frac{1}{{10}}{\text{ day}}{\text{.}} \cr} $$
Hence, the whole work is complete in $${\text{26}}\frac{1}{{10}}$$ days out of which A worked for 9 days,
B worked for 9 days and C worked for $${\text{8}}\frac{1}{{10}}$$ days.
Ratio of wages of A, B and C = Ratio of work done by A, B and C
$$ = \left( {\frac{1}{{90}} \times 9} \right):\left( {\frac{1}{{40}} \times 9} \right)$$     : $$\left( {\frac{1}{{12}} \times 8\frac{1}{{10}}} \right)$$
$$\eqalign{ & = \frac{1}{{10}}:\frac{9}{{40}}:\frac{{27}}{{40}} \cr & = 4:9:27 \cr & \therefore {\text{A's share}} \cr & = {\text{Rs}}{\text{.}}\left( {\frac{4}{{40}} \times 240} \right) \cr & = {\text{Rs}}{\text{.24}} \cr & {\text{B's share}} \cr & = {\text{Rs}}{\text{.}}\left( {\frac{9}{{40}} \times 240} \right) \cr & = {\text{Rs}}.54 \cr & {\text{C's share}} \cr & = {\text{Rs}}{\text{.}}\left( {\frac{{27}}{{40}} \times 240} \right) \cr & = {\text{Rs}}{\text{.162}} \cr} $$
18
A job can be done by 3 skilled workmen in 20 days or by 5 boys in 30 days. How many days will they take if they work together ?
Discuss
Answer & Solution
Answer: Option D
Solution:
$$\eqalign{ & {\text{3 men's 1 day's work}} = \frac{1}{{20}} \cr & {\text{5 boy's 1 day's work}} = \frac{1}{{30}} \cr & \left( {{\text{3 men}} + {\text{5 boy}}} \right){\text{'s 1 day's work}} \cr & = \left( {\frac{1}{{20}} + \frac{1}{{30}}} \right) \cr & = \frac{5}{{60}} \cr & = \frac{1}{{12}} \cr} $$
∴ 3 men and 5 boys will complete the work in 12 days.
19
P is thrice as good a workman as Q and therefore able to finish a job in 48 days less than Q. Working together, they can do it in ?
Discuss
Answer & Solution
Answer: Option A
Solution:
Let time taken by P = x days
Then, time taken by Q = 3x days
∴ 3x - x = 48
⇒ 2x = 48
⇒ x = 24
∴ (P + Q)'s 1 day's work
$$\eqalign{ & = \frac{1}{{24}} + \frac{2}{{72}} \cr & = \frac{{3 + 1}}{{72}} \cr & = \frac{1}{{18}} \cr} $$
∴ Required time = 18 days
Alternate:
Ratio of times taken by P and Q = 1 : 3
The time difference is 3 - 1 = 2 days
while Q take 3 days and P takes 1 day
If difference of time is 2 days, Q takes 3 days
If difference of time is 48 days,
$$\eqalign{ & {\text{Q }}{\kern 1pt} {\text{takes}} = {\text{ }}{\kern 1pt} \left( {\frac{3}{2} \times 48} \right) \cr & \,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\, = 72\,{\kern 1pt} {\text{days}} \cr} $$
So, P takes 24 days to do the work.
$$\eqalign{ & {\text{P's 1 day's work}} = \frac{1}{{24}} \cr & {\text{Q's 1 day's work}} = \frac{1}{{72}} \cr & \left( {{\text{P + Q}}} \right){\text{'s 1 day's work}} \cr & {\text{ = }}\left( {\frac{{\text{1}}}{{24}}{\text{ + }}\frac{{\text{1}}}{{72}}} \right) = \frac{{\text{4}}}{{72}} = \frac{1}{{18}} \cr} $$
∴ A and B together can do the work in
$$\frac{{18}}{1} = {\text{18 }}{\kern 1pt} {\text{days}}$$
20
A does 20% less work than B. If A can complete a piece of work in $$7\frac{1}{2}$$ hours, then B can do it in ?
Discuss
Answer & Solution
Answer: Option B
Solution:
Let time taken by B = x
$${\text{Efficiency}} \propto \frac{1}{{{\text{Time}}\,{\text{taken}}}}$$
So, if B is 100% efficient. then A is 80% efficient
So,
$$\eqalign{ & \Rightarrow \frac{{80}}{{100}} = \frac{x}{{15/2}} \cr & \Rightarrow x = \frac{{80 \times 15}}{{100 \times 2}} \cr & \Rightarrow x = 6\,{\text{hours}} \cr} $$
Alternate:
Number of hours taken by A to finish the work = $$7\frac{1}{2}$$ hours = $$\frac{15}{2}$$ hours
Work done by A in one hour : $$\frac{2}{15}$$
Let number of hours taken by B to finish the work : $$\frac{1}{{\text{x}}}$$
A can work 20% less than B that is $$\frac{20}{100}$$  = $$\frac{4}{5}$$ times of B’s work.
$$\eqalign{ & {\text{Here,}}\,\frac{4}{5}:1 = \frac{2}{{15}}:\frac{1}{{\text{x}}} \cr & \frac{4}{5} = \frac{{2{\text{x}}}}{{15}} \cr & {\text{x}} = \frac{{15 \times 4}}{{5 \times 2}} = 6\,{\text{hours}} \cr} $$