ExamVeda
Login
Home
61
A 10 hectare field is reaped by 2 men, 3 women and 4 children together in 10 days. If working capabilities of a man, a woman and a child are in the ratio 5 : 4 : 2, then a 16 hectare field will be reaped by 6 men, 4 women and 7 children in = ?
Discuss
Answer & Solution
Answer: Option D
Solution:
According to the question,
Efficiency of a man, a woman and a child are
$$\eqalign{ & 5:4:2{\text{ units/day}} \cr & {\text{One day work of 2 men}} \cr & = 2 \times 5 \cr & = 10{\text{ units}} \cr & {\text{One day work of 3 women}} \cr & = 3 \times 4 \cr & = 12{\text{ units}} \cr & {\text{One day work of 4 children}} \cr & = 4 \times 2 \cr & = 8{\text{ units}} \cr} $$
Applying formula, let time taken is D days.
$$\frac{{\left( {10 + 12 + 8} \right) \times {{10}_{{\text{days}}}}}}{{{{10}_{{\text{hectare}}}}}} = $$     $$\left[ {\frac{{\left( {{6_{{\text{men}}}} \times 5} \right) + \left( {{4_{{\text{women}}}} \times 4} \right) + \left( {{7_{{\text{children}}}} \times 2} \right) \times {\text{D}}}}{{{{16}_{{\text{hectare}}}}}}} \right]$$
$$\eqalign{ & \Leftrightarrow \frac{{\left( {30} \right) \times 10}}{{10}} = \frac{{\left[ {60} \right] \times {\text{D}}}}{{16}} \cr & \Leftrightarrow {\text{D}} = 8{\text{ days}} \cr} $$
62
If p men working p hours per day for p days produce p units of work, then the units of work produced by n men working n hours a day for days is = ?
Discuss
Answer & Solution
Answer: Option D
Solution:
Applying formula
Let work done by 'n' men and women
$$\frac{{{{\text{p}}_{{\text{men}}}} \times {{\text{p}}_{{\text{hours}}}} \times {{\text{p}}_{{\text{days}}}}}}{{{{\text{p}}_{{\text{units}}}}}} = $$     $$\frac{{{{\text{n}}_{{\text{men}}}} \times {{\text{n}}_{{\text{hours}}}} \times {{\text{n}}_{{\text{days}}}}}}{{{{\text{W}}_{{\text{units}}}}}}$$
$$\eqalign{ & \Leftrightarrow {{\text{p}}^{\text{2}}} = \frac{{{{\text{n}}^{\text{3}}}}}{{\text{w}}} \cr & \Leftrightarrow {\text{W}} = \frac{{{{\text{n}}^{\text{3}}}}}{{{{\text{p}}^{\text{2}}}}} \cr} $$
63
If two persons, with equal abilities, can do two jobs in two days then 100 persons with equal abilities can do 100 similar jobs in = ?
Discuss
Answer & Solution
Answer: Option D
Solution:
$$\frac{{{{\text{2}}_{{\text{person}}}} \times {{\text{2}}_{{\text{days}}}}}}{{{{\text{2}}_{{\text{jobs}}}}}} = \frac{{{\text{100}} \times {\text{D}}}}{{{\text{10}}{{\text{0}}_{{\text{jobs}}}}}}$$      (D is number of days required)
$$\eqalign{ & {\text{After solving}} \cr & {\text{D}} = 2{\text{ days}} \cr} $$
64
A is twice as good a workman as B. If they work together, they can complete a job in 18 days. If A alone does the job, in how many days he will complete the job ?
Discuss
Answer & Solution
Answer: Option A
Solution:
(A's 1 day's work) : (B's 1 day's work)
$$\eqalign{ & = 2:1 \cr & \left( {{\text{A}} + {\text{B}}} \right){\text{'s 1 day's work}} = \frac{1}{{18}} \cr & \therefore {\text{A's 1 day's work}} \cr & = \left( {\frac{1}{{18}} \times \frac{2}{3}} \right) \cr & = \frac{1}{{27}} \cr} $$
Hence, A alone can finish the work in 27 days.
65
A is thrice as good a workman as B and so takes 60 days less than B for doing a job. The time in which they can do the job together is = ?
Discuss
Answer & Solution
Answer: Option A
Solution:
Ratio of times taken by A and B = 1 : 3
If difference of time is 2 days, B takes 3 days
If difference of time is 60 days, B takes
$$\eqalign{ & = \left( {\frac{3}{2} \times 60} \right) \cr & = {\text{90 days}} \cr} $$
So, A takes 30 days to do the work
$$\eqalign{ & {\text{A's 1 day's work}} = \frac{1}{{30}} \cr & {\text{B's 1 day's work}} = \frac{1}{{90}} \cr & \left( {{\text{A}} + {\text{B}}} \right){\text{'s 1 day's work}} \cr & = \left( {\frac{1}{{30}} + \frac{1}{{90}}} \right) \cr & = \frac{4}{{90}} \cr & = \frac{2}{{45}} \cr} $$
∴ A and B together can do the job in
$$\eqalign{ & = \frac{{45}}{2} \cr & = 22\frac{1}{2}\,{\text{days}} \cr} $$
66
A and B can do a job in 7 days. A is $${\text{1}}\frac{3}{4}$$ times as efficient as B. The same job can be done by A alone in ?
Discuss
Answer & Solution
Answer: Option B
Solution:
(A's 1 day's work) : (B's 1 day's work)
$$\eqalign{ & = \frac{7}{4}:1 \cr & = 7:4 \cr} $$
Let A's and B's 1 day's work be 7x and 4x respectively
Then,
$$\eqalign{ & 7x + 4x = \frac{1}{7} \cr & \Rightarrow 11x = \frac{1}{7} \cr & \Rightarrow x = \frac{1}{{77}} \cr & \therefore {\text{A's 1 day's work}} \cr & = \left( {\frac{1}{{77}} \times 7} \right) \cr & = \frac{1}{{11}} \cr} $$
Hence, A alone can do the job in 11 days.
67
A road of 5 m length will be constructed in 100 days. So, 280 workers were employed. But after 80 days it was found that only $${\text{3}}\frac{1}{2}$$ km road was completed. Now how many more people were need to finish the work in the specified time ?
Discuss
Answer & Solution
Answer: Option C
Solution:
Let 'n' more number of man are required to complete the job in 20 day.
$$\frac{{{{80}_{{\text{days}}}} \times {\text{28}}{{\text{0}}_{{\text{worker}}}}}}{{{\text{3}}{\text{.5 km}}}} = $$     $$\frac{{{{\left( {{\text{280}} + {\text{n}}} \right)}_{{\text{worker}}}} \times {\text{2}}{{\text{0}}_{{\text{days}}}}}}{{{\text{1}}{\text{.5 km}}}}$$
$$\eqalign{ & {\text{After solving:}} \cr & \Rightarrow 480 = 280 + {\text{n}} \cr & \Rightarrow {\text{n}} = 200 \cr} $$
68
If the work done by (x - 1) men in (x + 1) days and the work done by (x + 2) men in (x - 1) days are in the ratio 9 : 10, then the value of x is equal to ?
Discuss
Answer & Solution
Answer: Option D
Solution:
Put values in formula
$$\frac{{{{\left( {x - 1} \right)}_{{\text{men}}}} \times {{\left( {x + 1} \right)}_{{\text{days}}}}}}{{{{\text{9}}_{{\text{work}}}}}} = $$       $$\frac{{{{\left( {x + 2} \right)}_{{\text{men}}}} \times {{\left( {x - 1} \right)}_{{\text{days}}}}}}{{{{10}_{{\text{work}}}}}}$$
$$\eqalign{ & \Rightarrow \frac{{x + 1}}{9} = \frac{{x + 2}}{{10}} \cr & \Rightarrow 10x + 10 = 9x + 18 \cr & \Rightarrow x = 8 \cr} $$
69
A can do a piece of work in 70 days and B is 40% more efficient then A. Then the number of days taken by B to do the same work is = ?
Discuss
Answer & Solution
Answer: Option C
Solution:
  A   :   B
Efficiency →   100% : 140%
  5 : 7
     
Time 7 : 5
  ×10↓   ↓×10
Actual Time   70 days   50 days
70
A can do a certain work in 12 days. B is 60% more efficient then A. How many days will B and A together take to do the same job?
Discuss
Answer & Solution
Answer: Option D
Solution:
Time taken by B to complete the work
$$\eqalign{ & = 12 \times \frac{{100}}{{160}} \cr & = \frac{{15}}{2}\,{\text{days}} \cr} $$
∴ (A + B)'s 1 day's work
$$\eqalign{ & = \frac{1}{{12}} + \frac{2}{{15}} \cr & = \frac{{5 + 8}}{{60}} \cr & = \frac{{13}}{{60}} \cr} $$
Hence, the work will be completed in $$\frac{{60}}{{13}}$$ days
Alternate:
Ratio of time, taken by A and B = 160 : 100 = 8 : 5
If A takes 8 days, B takes 5 days.
If A takes 12 days, B takes = $$\frac{5}{8} \times 12 = \frac{{ 15}}{2}$$
Time take by A = 12 days
Time take by B = 7.5 days
L.C.M. of Total Work = 60
Ratio of time, taken by A and B = 8 : 5
Time taken by A and B together to complete the task
$$ = \frac{{60}}{{13}}{\text{days}}$$