ExamVeda
Login
Home
71
Kamal can do a work in 15 days. Bimal is 50% more efficient then Kamal. The number of days, Bimal will take to do the same piece of work, is = ?
Discuss
Answer & Solution
Answer: Option B
Solution:
Ratio of times taken by Kamal and Bimal
$$\eqalign{ & = 150:100 \cr & = 3:2 \cr} $$
Suppose Bimal takes x days to do the work
$$\eqalign{ & \Rightarrow 3:2::15:x \cr & \Rightarrow x = \left( {\frac{{2 \times 15}}{3}} \right) \cr & \Rightarrow x = 10{\text{ days}}{\text{.}} \cr} $$
72
A does 20% less work than B. If A can complete a piece of work in $${\text{7}}\frac{1}{2}$$ hours, then B can do it in ?
Discuss
Answer & Solution
Answer: Option C
Solution:
Ratio of times taken by A and B
$$\eqalign{ & = 100:80 \cr & = 5:4 \cr} $$
Suppose B takes x hours to do the work
$$\eqalign{ & \Rightarrow 5:4::\frac{{15}}{2}:x \cr & \Rightarrow x = \left( {\frac{{4 \times 15}}{{2 \times 5}}} \right) \cr & \Rightarrow x = 6{\text{ hours}}{\text{}} \cr} $$
73
A, B and C can separately do a work in 12, 15 and 20 days respectively. They started to work together but C left after 2 days. The remaining work will be finished in = ?
Discuss
Answer & Solution
Answer: Option A
Solution:
$$\eqalign{ & \left( {{\text{A}} + {\text{B}} + {\text{C}}} \right){\text{'s 1 day's work}} \cr & = \left( {\frac{1}{{12}} + \frac{1}{{15}} + \frac{1}{{20}}} \right) \cr & = \frac{{12}}{{60}} \cr & = \frac{1}{5} \cr & \left( {{\text{A}} + {\text{B}} + {\text{C}}} \right){\text{'s 2 day's work}} \cr & = \left( {\frac{1}{5} \times 2} \right) \cr & = \frac{2}{5} \cr & {\text{Remaining work }} \cr & = \left( {1 - \frac{2}{3}} \right) \cr & = \frac{3}{5}{\text{ }} \cr & \left( {{\text{A}} + {\text{B}}} \right){\text{'s 1 day's work}} \cr & = \left( {\frac{1}{{12}} + \frac{1}{{15}}} \right) \cr & = \frac{9}{{60}} = \frac{3}{{20}} \cr & {\text{Now, }}\frac{3}{{20}}{\text{ work is done by A and B in 1 day}} \cr & \therefore \frac{3}{5}\,{\text{work is done by A and B in }} \cr & = \left( {\frac{{20}}{3} \times \frac{3}{5}} \right) \cr & = 4{\text{ days}}{\text{.}} \cr} $$
74
A can do a piece of work in 15 days, which B can do it in 10 days. B worked at it for 8 days. A can finish the remaining work in?
Discuss
Answer & Solution
Answer: Option B
Solution:
$$\eqalign{ & {\text{B's 8 day's work}} \cr & = \left( {\frac{1}{{10}} \times 8} \right) \cr & = \frac{4}{5} \cr & {\text{Remaining work}} \cr & = \left( {1 - \frac{4}{5}} \right) \cr & = \frac{1}{5} \cr & {\text{Now,}} \cr & \frac{1}{{15}}{\text{work is done by A in 1 day}}{\text{.}} \cr & \therefore \frac{1}{5}{\text{ work is done by A in}} \cr & = \left( {15 \times \frac{1}{5}} \right) \cr & = 3{\text{ days}}{\text{.}} \cr} $$
75
A does half as much work as B in one-sixth of the time. If together they take 10 days to complete a work. How much time shall B alone take to do it ?
Discuss
Answer & Solution
Answer: Option B
Solution:
Suppose B takes x days to do the work.
$$\eqalign{ & {\text{A takes}} = \left( {2 \times \frac{1}{6}x} \right) \cr & = \frac{1}{3}x{\text{ days to do it}}{\text{.}} \cr & \left( {{\text{A}} + {\text{B}}} \right){\text{'s 1 day's work}} = \frac{1}{{10}} \cr & \Rightarrow \frac{1}{x} + \frac{3}{x} = \frac{1}{{10}} \cr & \Rightarrow \frac{4}{x} = \frac{1}{{10}} \cr & \Rightarrow x = 40{\text{ days}}{\text{.}} \cr} $$
76
Some carpenters promised to do a job in 9 days but 5 of them were absent and remaining men did the job in 12 day. The original number of carpenters was ?
Discuss
Answer & Solution
Answer: Option B
Solution:
Let there were N carpenters in the beginning
According to the question,
$$\frac{{{{\text{N}}_{{\text{men}}}} \times {9_{{\text{days}}}}}}{{{{\text{1}}_{{\text{work}}}}}} = $$     $$\frac{{{{\left( {{\text{N}} - 5} \right)}_{{\text{men}}}} \times {{12}_{{\text{days}}}}}}{{{{\text{1}}_{{\text{work}}}}}}$$
$$\eqalign{ & {\text{3N}} = {\text{4N}} - 20 \cr & {\text{N}} = {\text{20 men}} \cr} $$
77
If 4 men or 6 women can do a piece of work in 12 days working 7 hours a day, how many days will it take to complete a work twice as large with 10 men and 3 women working together 8 hours a day ?
Discuss
Answer & Solution
Answer: Option B
Solution:
According to the question,
4 men = 6 women
2 men = 3 women
10 men + 3 women = 10 men + 2 men
10 men + 3 women = 12 men.....(i)
$$\frac{{{4_{{\text{men}}}} \times {{12}_{{\text{days}}}} \times {7_{{\text{hours}}}}}}{{{{\text{1}}_{{\text{work}}}}}} = $$      $$\frac{{{{12}_{{\text{men}}}} \times {{\text{D}}_{{\text{days}}}} \times {8_{{\text{hours}}}}}}{{{{\text{1}}_{{\text{work}}}}}}$$
$$\eqalign{ & {\text{After solving we get}} \cr & {\text{D}} = 7{\text{ days}} \cr} $$
78
A contractor undertook to finish a work in 92 days and employed 110 men. After 48 days, he found that he had already done $$\frac{3}{5}$$ part of the work, the number of men he can withdraw so that his work may still be finished in time is ?
Discuss
Answer & Solution
Answer: Option D
Solution:
Let 'n' number of men can be withdrawn
$$\eqalign{ & \frac{{\left( {{{110}_{{\text{men}}}} \times {{48}_{{\text{days}}}}} \right)}}{{\frac{3}{5}{\text{work}}}} = \frac{{\left( {110 - {\text{n}}} \right) \times 44}}{{\frac{2}{5}{\text{work}}}} \cr & \Rightarrow 110 \times 16 = \left( {110 - {\text{n}}} \right) \times 22 \cr & \Rightarrow 160 = \left( {110 - {\text{n}}} \right) \times 2 \cr & \Rightarrow {\text{n}} = 30 \cr} $$
79
A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. The number of additional men that should be appointed so that the whole work will be finished in time is = ?
Discuss
Answer & Solution
Answer: Option B
Solution:
Let 'n' number of men can required
$$\eqalign{ & \frac{{\left( {{{200}_{{\text{men}}}} \times {{50}_{{\text{days}}}}} \right)}}{{\frac{1}{4}}} = \frac{{\left( {200 + {\text{n}}} \right) \times {{100}_{{\text{days}}}}}}{{\frac{3}{4}}} \cr & \Rightarrow 3 \times 100 = \left( {200 + {\text{n}}} \right) \cr & \Rightarrow {\text{n}} = 100 \cr} $$
80
A can complete a piece of work in 18 days, B in 20 days and C in 30 days. B and C together start the work and are forced to leave after 2 days. The time taken by A alone to complete the remaining work is ?
Discuss
Answer & Solution
Answer: Option C
Solution:
$$\eqalign{ & \left( {{\text{B}} + {\text{C}}} \right){\text{'s 1 day's work}} \cr & = \left( {\frac{1}{{20}} + \frac{1}{{30}}} \right) \cr & = \frac{5}{{60}} \cr & = \frac{1}{{12}} \cr & \left( {{\text{B}} + {\text{C}}} \right){\text{'s 2 day's work}} \cr & = \left( {\frac{1}{{12}} \times 2} \right) \cr & = \frac{1}{6} \cr & {\text{Remaining work }} \cr & = \left( {1 - \frac{1}{6}} \right) \cr & = \frac{5}{6}{\text{ }} \cr & \left( {{\text{A}} + {\text{B}}} \right){\text{'s 1 day's work}} \cr & = \left( {\frac{1}{{12}} + \frac{1}{{15}}} \right) \cr & = \frac{9}{{60}} \cr & = \frac{3}{{20}} \cr} $$
Now, $$\frac{1}{{18}}$$ work is done by A in 1 day
$$\eqalign{ & \therefore \frac{5}{6}{\text{ work is done by A in }} \cr & = \left( {18 \times \frac{5}{6}} \right) \cr & = 15{\text{ days}} \cr} $$