P and Q together can do a work in 12 days. P alone can do the same work in 36 days. In how many days can Q alone complete two-third part of the same work?
Answer & Solution
Correct Answer:
Option
A

Efficiency of Q = 2
So, required answer = $$\frac{{36 \times \frac{2}{3}}}{2}$$ = 12 days