If 27 people, working 8 hours a day, can complete a task in 12 days, then in how many days will 18 people finish the task, working 9 hours a day?
Answer & Solution
Correct Answer:
Option
C
27 × 8 × 12 = 18 × 9 × x
x = 16 days
x = 16 days