Assertion A: When rock conditions are favorable, it will not be necessary to take up concrete lining concurrently with the driving operations till the full length of the tunnel has been driven through rock.
Reason R: A tunnel through rock, hard or soft, does not need any concrete lining
Select your answer
A. Both A and R is true and R is the correct explanation of A
B. Both A and R is true but R is not the correct explanation of A
C. A is true but R is false
D. A is false but R is true
Answer: Option C
Related Questions on Tunnel Engineering
A. (i) and (ii) are correct
B. (iii) and (iv) are correct
C. (i) and (iv) are correct
D. (ii) and (iii) are correct
Which of the following lining material is useful for shield driven tunnels in sub aqueous regions?
A. Stone masonry
B. Timber
C. Cast iron
D. Cement concrete
Which of the following methods of tunneling is used for long tunnels at great depths?
A. Army method
B. Needle beam method
C. Austrian method
D. English method
A. Only up holes
B. Only down holes
C. Horizontal or up holes
D. Horizontal down or up holes
Join The Discussion