__________ charts are used to represent the project tasks and durations.
A. Gantt
B. X ray
C. Bar
D. Scatter
Answer: Option A
Solution(By Examveda Team)
Gantt charts are used to represent the project tasks and durations. A gantt chart is a horizontal bar chart that visually represents a project plan over time. Modern gantt charts typically show you the status of as well as who's responsible for each task in the project.Related Questions on Management Information System (MIS)