ExamVeda
Login
Home
91
In uneven cash flow, 'IRR' is an abbreviation of an
Discuss
Answer & Solution
Answer: Option A
Solution:
In uneven cash flow, 'IRR' is an abbreviation of an internal rate of return. The internal rate of return (IRR) is a metric used in capital budgeting to estimate the profitability of potential investments.
92
A company who issues bonds or stocks in result raised funds which finally
Discuss
Answer & Solution
Answer: Option C
Solution:
A company who issues bonds or stocks in result raised funds which finally increases cash.
93
During planning period, a marginal cost for raising a new debt is classified as
Discuss
Answer & Solution
Answer: Option B
Solution:
During planning period, a marginal cost for raising a new debt is classified as relevant cost. Relevant cost is a managerial accounting term that describes avoidable costs that are incurred when making business decisions. The concept of relevant cost is used to eliminate unnecessary data that could complicate the decision-making process.
94
Cost of common stock is 14% and bond risk premium is 9% then bond yield will be
Discuss
Answer & Solution
Answer: Option B
Solution:
Bond yield = Cost of common stock - Bond risk premium
= 14% - 9% = 5.00%
95
In weighted average cost of capital, a company can affect its capital cost through
Discuss
Answer & Solution
Answer: Option D
Solution:
In weighted average cost of capital, a company can affect its capital cost through policy of capital structure, policy of dividends and policy of investment
96
A risk associated with project and way considered by well diversified stockholder is classified as
Discuss
Answer & Solution
Answer: Option B
Solution:
A risk associated with project and way considered by well diversified stockholder is classified as beta risk. Beta is a measure of the volatility, or systematic risk, of a security or a portfolio in comparison to the market as a whole. Beta risk is the probability that a false null hypothesis will be accepted by a statistical test.
97
Cost of common stock is 13% and bond risk premium is 5% then bond yield would be
Discuss
Answer & Solution
Answer: Option C
Solution:
Bond Yeild = Cost of common stock - Bond risk premium
= 13% - 5% = 8%.
98
Variability for expected returns for projects is classified as
Discuss
Answer & Solution
Answer: Option B
Solution:
Variability for expected returns for projects is classified as stand-alone risk. Standalone risk measures the dangers associated with a single facet of a company's operations or by holding a specific asset, such as a closely-held corporations. In portfolio management, standalone risk measures the undiversified risk of an individual asset.
99
Cost of common stock is 16% and bond yield is 9% then bond risk premium would be
Discuss
Answer & Solution
Answer: Option A
Solution:
Bond risk premium = Cost of common stock - Bond Yeild
= 16% - 9% = 7%.
100
If future return on common stock is 14% and rate on T-bonds is 5% then current market risk premium will be
Discuss
Answer & Solution
Answer: Option B
Solution:
Current Market Risk Premium = Future return on common stock - T-Bond
= 14% - 5% = 9%.