Consider the following assembly line problem:
time_to_reach[2][3] = {{17, 2, 7}, {19, 4, 9}}
time_spent[2][4] = {{6, 5, 15, 7}, {5, 10, 11, 4}}
entry_time[2] = {8, 10}
exit_time[2] = {10, 7}
num_of_stations = 4
For the optimal solution, which should be the starting assembly line?
time_to_reach[2][3] = {{17, 2, 7}, {19, 4, 9}}
time_spent[2][4] = {{6, 5, 15, 7}, {5, 10, 11, 4}}
entry_time[2] = {8, 10}
exit_time[2] = {10, 7}
num_of_stations = 4A. Line 1
B. Line 2
C. All of the mentioned
D. None of the mentioned
Answer: Option B