Examveda
Examveda

"Consider the following situations.
1.Soil is soft.
2.Volume of existing surface traffic on the alignment is heavy.
3.Track is at a deeper level.
4.Water table is high.
In the construction of Metro Railways, “Cut and Cover” method of construction is suitable in situations listed at "

A. 1 and 2

B. 1 and 3

C. 1 and 4

D. 2 and 3

Answer: Option C


This Question Belongs to Civil Engineering >> Tunnel Engineering