CPM has following time estimate
A. One time estimate
B. Two time estimate
C. Three time estimate
D. Four time estimate
Answer: Option A
Solution(By Examveda Team)
CPM has one time estimateJoin The Discussion
Comments ( 1 )
Related Questions on Industrial Engineering and Production Management
The essential condition for the decompression of an activity is that
A. The project time should change due to decompression
B. After decompression the time of an activity invariably exceeds its normal time
C. An activity could be decompressed to the maximum extent of its normal time
D. None of the above
A. CAM < DAM
B. CAM > DAM
C. CAM = DAM
D. There is no such criterion
Sir Auto Cad kai object questions nhi hai