Critical path on PERT/CPM chart is obtained by joining the events having

Answer & Solution
Correct Answer: Option B
Slack time can be defined as the amount of time an task can be delayed without causing another task to be delayed or impacting the completion date of your project.
Critical path on PERT/CPM chart is obtained by joining the events having Minimum slack
Examveda
Question posted by Examveda
Community

Join the Discussion

2 Comments
Dr. Akash
Dr. Akash 3 years ago
Explan
Sarveshwer Chandra
Sarveshwer Chandra 6 years ago
No slack