Dummy activities are used to
A. Determine the critical path
B. Determine the project completion time
C. Maintain the required net work
D. None of these
Answer: Option C
Solution(By Examveda Team)
Dummy activities are used to Maintain the required net workRelated Questions on Industrial Engineering and Production Management
The essential condition for the decompression of an activity is that
A. The project time should change due to decompression
B. After decompression the time of an activity invariably exceeds its normal time
C. An activity could be decompressed to the maximum extent of its normal time
D. None of the above
A. CAM < DAM
B. CAM > DAM
C. CAM = DAM
D. There is no such criterion