During whose reign, the UT Jammu and Kashmir got its first Hydro-Electric Project at Mohra?

Answer & Solution
Correct Answer: Option C
During Maharaja Pratap Singh reign, Jammu and Kashmir got its first Hydro - Electric Project at Mohra. It is about 22.5 km from Baramulla towards Uri.