Earliest finish time can be regarded as
A. Earliest start time + duration of activity
B. Earliest start time - duration of activity
C. Latest finish time + duration of activity
D. Latest finish time - duration of activity
Answer: Option A
Solution(By Examveda Team)
Earliest finish time can be regarded as, earliest start time + duration of activity.Related Questions on Industrial Engineering and Production Management