For providing a raft foundation, the following activities are involved
i) Ramming the foundation bed
ii) Excavation of the soil upto required depth
iii) Laying the reinforcement over the foundation bed
iv) Curing the cement concrete placed over reinforcement
v) Pouring the cement concrete over the reinforcement
The correct sequence is
A. i, ii, iii, iv, v
B. v, iv, iii, ii, i
C. ii, i, iii, v, iv
D. iii, ii, v, i, iv
Answer: Option C