Gantt chart provides information about the
A. Material handling
B. Proper utilization of manpower
C. Production schedule
D. Efficient working of machine
Answer: Option C
Solution(By Examveda Team)
A Gantt chart is a type of bar chart that illustrates a project schedule.This chart lists the tasks to be performed on the vertical axis, and time intervals on the horizontal axis.
The width of the horizontal bars in the graph shows the duration of each activity.
Related Questions on Industrial Engineering and Production Management
The essential condition for the decompression of an activity is that
A. The project time should change due to decompression
B. After decompression the time of an activity invariably exceeds its normal time
C. An activity could be decompressed to the maximum extent of its normal time
D. None of the above
A. CAM < DAM
B. CAM > DAM
C. CAM = DAM
D. There is no such criterion