If 10 men can do a piece of work in 12 days, the time taken by 12 men to do the same piece of work will be:

A. 12 days

B. 10 days

C. 9 days

D. 8 days

Answer: Option B

Solution(By Examveda Team)

Here, we use work equivalence method;
10 × 12 = 12 × x
Or, x = 10 days

To understand the work equivalence method, we use a graphic as follows:

Men   Days
10 ↓    12
12     ↑ x (let)
Here, the two arrows, downward (↓) and upward (↑) show variation between men and days.
[If downward arrows show decrements then upward arrows show increments and vice-verse.]
Thus,
$$\eqalign{ & \frac{{10}}{{12}} = \frac{{\text{x}}}{{12}} \cr & {\text{or, x}} = \frac{{10 \times 12}}{{12}} \cr & \,\,\,\,\,\,\,\,\,\,\,\,\, = 10\,{\text{days}} \cr} $$

This Question Belongs to Arithmetic Ability >> Time And Work

Join The Discussion

Comments ( 1 )

  1. Nilesh Barke
    Nilesh Barke :
    3 years ago

    M1*D1 = M2*D2
    10*12 = 12*D2
    D2 = 120/ 12
    D2 = 10