If 2 men or 3 women or 4 boys can do a piece of work in 52 days, then the same piece of work will be done by 1 man, 1 woman and 1 boy in:

A. 48 days

B. 36 days

C. 45 days

D. 50 days

Answer: Option A

Solution(By Examveda Team)

Work done by 2 men = 3 women = 4 boys
1 man = 2 boys
1 woman = $$\frac{4}{3}$$ boys
Thus,
Boys × days = 4 × 52 boys × days
Again,
1 man + 1 women + 1 boys,
$$ = 2 + \frac{4}{3} + 1$$
$$ = \frac{{13}}{3}$$  boys
Using work equivalent method,
boys × day = BOYS × DAYS
$$4 \times 52 = \frac{{13}}{3} \times {\text{x}}\,{\text{(let)}}$$
x = 48 days

This Question Belongs to Arithmetic Ability >> Time And Work

Join The Discussion

Comments ( 9 )

  1. Mayank Mahir
    Mayank Mahir :
    3 months ago

    One man can complete a work in 16 days. One woman can complete the same work in 24 days. If 4 men and 6 women are employed simultaneously, the work can be completed in

  2. Praveen Singh
    Praveen Singh :
    5 years ago

    37 mens work 4 days earn 1024 , 15 people how many days they work and earn 768

  3. Please Smile
    Please Smile :
    6 years ago

    2M =3W =4B

    TAKE LCM - 12

    M : W : B
    6: 4 :3

    T.W = 52(6*2) = 52*12 = 624
    D (1M+1W+1B) = 624
    D(1*6+ 1*4+1*3)=624
    DAYs = 624/13 = 48 DAYS

  4. Lakshmi Keerthana
    Lakshmi Keerthana :
    6 years ago

    You given 5women and you done it with 3women

  5. Pravakar Kapei
    Pravakar Kapei :
    7 years ago

    3 men or 4 women or 5 boy can do a job in 47 day.then in how many days will 1 men, 1women,and 1 boy do the job

  6. Sam Sam
    Sam Sam :
    7 years ago

    A 60% of work in 15 days. he then call B they together finish theremaingwork in 5 days. How long B would take to do whole work??

  7. D D
    D D :
    7 years ago

    Qyestion is weong : it must be 3 women

  8. Kumar Chandan
    Kumar Chandan :
    8 years ago

    What's your method @Goutam Chandra?

  9. Goutam Chandra
    Goutam Chandra :
    8 years ago

    complex method

Related Questions on Time and Work