If 450 men can finish construction of an apartment in 20 days, then how many men are needed to complete the same work in 30 days?

A. 150

B. 300

C. 400

D. 250

Answer: Option B

Solution(By Examveda Team)

450 men × 20 = x men × 30
x = 300 men