If ‘a’ is the base amount expenditure, ‘b’ is the increase in the operation cost each year over a period of’ 'n’ years, the total cost of maintenance is:
A. a + (n + 1) b
B. a + (n - 1) b
C. a × (n - 1) b
D. a - (n - 1) b
Answer: Option B