If E is the duration, ES and EF are die earliest start and finish times, LS and LF are latest start and finish times, then the following relation holds good

A. EF = ES + D

B. LS = LFD

C. LF = LS + D

D. All of the above

Answer: Option D

Solution(By Examveda Team)

If E is the duration, ES and EF are die earliest start and finish times, LS and LF are latest start and finish times, then the following relation holds good
- EF = ES + D
- LS = LFD
- LF = LS + D

Join The Discussion

Comments ( 1 )

  1. HARENDRA KUMAR
    HARENDRA KUMAR :
    4 years ago


    If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good

    A. EF = ES + D
    B. LS = LF - D
    C. LF = LS + D
    D. D = EF - ES
    E. all the above.