If E is the duration, ES and EF are die earliest start and finish times, LS and LF are latest start and finish times, then the following relation holds good
A. EF = ES + D
B. LS = LFD
C. LF = LS + D
D. All of the above
Answer: Option D
Solution(By Examveda Team)
If E is the duration, ES and EF are die earliest start and finish times, LS and LF are latest start and finish times, then the following relation holds good- EF = ES + D
- LS = LFD
- LF = LS + D
Join The Discussion
Comments ( 1 )
Related Questions on Industrial Engineering and Production Management
The essential condition for the decompression of an activity is that
A. The project time should change due to decompression
B. After decompression the time of an activity invariably exceeds its normal time
C. An activity could be decompressed to the maximum extent of its normal time
D. None of the above
A. CAM < DAM
B. CAM > DAM
C. CAM = DAM
D. There is no such criterion
If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good
A. EF = ES + D
B. LS = LF - D
C. LF = LS + D
D. D = EF - ES
E. all the above.