If flexible budget variance is $105000, actual cost is $65000 then flexible budget cost will be
A. $40,000
B. $50,000
C. $150,000
D. $170,000
Answer: Option A
Solution (By Examveda Team)
Flexible budget cost = Flexible budget variance - Actual cost= $105000 - $65000
= $40000.