ExamVeda
Login
Home
This question belongs to Management Management Accounting
Management Accounting
?

If flexible budget variance is $95000 and an actual cost is $40000, then flexible budget cost would be

Answer & Solution
Correct Answer: Option D
Flexible budget cost = Flexible budget variance - An actual cost
= $95000 - $40000 = $55,000.