If m men can do a work in r days, then the number of days taken by (m + n) men to do it is :

A. $$\frac{{{\text{m}} + {\text{n}}}}{{{\text{mn}}}}$$

B. $$\frac{{{\text{m}} + {\text{n}}}}{{{\text{mr}}}}$$

C. $$\frac{{{\text{mr}}}}{{{\text{m}} + {\text{n}}}}$$

D. $$\frac{{{\text{r}}\left( {{\text{m}} + {\text{n}}} \right)}}{{{\text{mn}}}}$$

Answer: Option C

Solution(By Examveda Team)

M1 × D1 = M2 × D2
mr = (m +n) × D2
D2 = $$\frac{{{\text{mr}}}}{{{\text{m}} + {\text{n}}}}$$