If m men can do a work in r days, then the number of days taken by (m + n) men to do it is :
Answer & Solution
Correct Answer:
Option
C
M1 × D1 = M2 × D2
mr = (m +n) × D2
D2 = $$\frac{{{\text{mr}}}}{{{\text{m}} + {\text{n}}}}$$