If manufacturing cycle efficiency is 0.725 and total manufacturing time is 45 minute, then value added manufacturing time will be

A. 42.625

B. 36.724

C. 32.625

D. 41.625

Answer: Option C

Solution(By Examveda Team)

Value added manufacturing time = Manufacturing cycle efficiency × Total manufacturing time
= 0.725 × 45
= 32.625.