If manufacturing cycle efficiency is 0.725 and total manufacturing time is 45 minute, then value added manufacturing time will be

Answer & Solution
Correct Answer: Option C
Value added manufacturing time = Manufacturing cycle efficiency × Total manufacturing time
= 0.725 × 45
= 32.625.