In case of repudiation of a contract of sale of goods before the date of delivery, under section 60 of the Sale of Goods Act, 1930, where the delivery was to be made by instalments, the measure of damages is
A. The difference between the contract price and the market price on the date when first delivery was to be made
B. The difference between the contract price and the market price on the date when last delivery was to be made
C. The difference between the contract price and the market price on several days when the goods ought to have been accepted or delivered
D. Either (A) or (B)
Answer: Option C