In crash program for a project

A. both direct and indirect costs, increase

B. indirect costs increase and direct costs decrease

C. direct costs increase and indirect costs decrease

D. cost is no criterion

Answer: Option C

Solution(By Examveda Team)

In crash program for a project direct costs increase and indirect costs decrease