In crash program for a project
A. both direct and indirect costs, increase
B. indirect costs increase and direct costs decrease
C. direct costs increase and indirect costs decrease
D. cost is no criterion
Answer: Option C
Solution(By Examveda Team)
In crash program for a project direct costs increase and indirect costs decreaseRelated Questions on Industrial Engineering and Production Management
The essential condition for the decompression of an activity is that
A. The project time should change due to decompression
B. After decompression the time of an activity invariably exceeds its normal time
C. An activity could be decompressed to the maximum extent of its normal time
D. None of the above
A. CAM < DAM
B. CAM > DAM
C. CAM = DAM
D. There is no such criterion
Join The Discussion