In method 3 the restoration is done by addition of ____________
A. Metal sleeve jacket
B. Aluminium jacket
C. Steel jacket
D. Water proof jacket
Answer: Option A
Solution(By Examveda Team)
Metal sleeve jacket is added in method 3 to do the restoration. In this method preload is applied before the repair of the damaged concrete and removed after the completion of repairs and a metal sleeve jacket is installed around and beyond the damaged area and the gap between the metal sleeve girders is filles with epoxy grout by pressure injection.Related Questions on Building Maintenance