In method 3 the restoration is done by addition of ____________

Answer & Solution
Correct Answer: Option A
Metal sleeve jacket is added in method 3 to do the restoration. In this method preload is applied before the repair of the damaged concrete and removed after the completion of repairs and a metal sleeve jacket is installed around and beyond the damaged area and the gap between the metal sleeve girders is filles with epoxy grout by pressure injection.