In the mid-section formula
A. The mean depth is the average of depths of two consecutive sections
B. The area of mid-sections is calculated by using mean depth
C. The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections
D. All of the above
Answer: Option D
Related Questions on Estimating and Costing
A. Mid-section formula
B. Trapezoidal formula
C. Prismoidal formula
D. All the above
Size, capacity and materials need be specified for
A. Bib-cocks
B. Stop-cocks
C. Ball valves
D. All the above
The expected out turn of 12 mm plastering with cement mortar is
A. 2.5 sq m
B. 4.0 sq m
C. 6.0 sq m
D. 8.0 sq m
A. Excavation
B. Surface dressing
C. Cutting
D. Surface excavation
Join The Discussion