Match the items of List I with List II and choose the correct answer of combination.
List-I (Critical Control Standards) List-II (Critical Points)
a. Physical standards 1. Material cost per unit
b. Cost standards 2. Labour hours per unit of output
c. Revenue standards 3. Timing of production
d. Program standards 4. Average sales per customer

Answer & Solution
Correct Answer: Option A