Performance rating is equal to
A. Observed performance + normal performance
B. Observed performance - normal performance
C. Observed performance × normal performance
D. None of the above
Answer: Option D
Solution(By Examveda Team)
Performance Rating can be defined as the procedure in which the time study engineer compares the performance of operator(s) under observation to the Normal Performance and determines a factor called Rating Factor.Related Questions on Industrial Engineering and Production Management
The essential condition for the decompression of an activity is that
A. The project time should change due to decompression
B. After decompression the time of an activity invariably exceeds its normal time
C. An activity could be decompressed to the maximum extent of its normal time
D. None of the above
A. CAM < DAM
B. CAM > DAM
C. CAM = DAM
D. There is no such criterion