PERT stands for
A. Program Estimation and Reporting Technique
B. Process Estimation and Review Technique
C. Program Evaluation and Review Technique
D. Planning Estimation and Resulting Technique
Answer: Option C
Solution(By Examveda Team)
PERT stands for Program Evaluation and Review TechniqueRelated Questions on Industrial Engineering and Production Management
The essential condition for the decompression of an activity is that
A. The project time should change due to decompression
B. After decompression the time of an activity invariably exceeds its normal time
C. An activity could be decompressed to the maximum extent of its normal time
D. None of the above
A. CAM < DAM
B. CAM > DAM
C. CAM = DAM
D. There is no such criterion