PERT/CPM, techniques can be used for following applications
A. Once through project
B. Maintenance jobs
C. Research and development
D. All of the above
Answer: Option D
Solution(By Examveda Team)
CPM is a statistical technique of project management in which planning, scheduling, organising, coordination and control of well-defined activities take place. PERT is a technique of planning and control of time.Related Questions on Industrial Engineering and Production Management
The essential condition for the decompression of an activity is that
A. The project time should change due to decompression
B. After decompression the time of an activity invariably exceeds its normal time
C. An activity could be decompressed to the maximum extent of its normal time
D. None of the above
A. CAM < DAM
B. CAM > DAM
C. CAM = DAM
D. There is no such criterion
Join The Discussion