Pessimistic time is
A. The maximum time which an activity might require
B. The average time required for a job
C. The most probable time considering all conditions
D. The minimum time in which an activity can possibly be accomplished
Answer: Option A
Solution(By Examveda Team)
Pessimistic time is a concept used in the program evaluation and review technique (PERT). It represents the longest estimated time period within which a task is likely to be completed, and is used in project planning.Related Questions on Industrial Engineering and Production Management