Pick up the correct statement from the following:

A. Over head rate = $$\frac{{{\text{total over head in rupees for period}}}}{{{\text{direct labour in rupees for period}}}}$$

B. Over head cost per unit = Overhead ratio × direct labour cost/unit

C. Both (A) and (B)

D. Neither (A) nor (B)

Answer: Option C