Pick up the correct statement from the following:
A. In order to check up the average depth of excavation, 'Dead man’s' are left at the mid-widths of borrow pits
B. The earthwork calculation in excavation is made from the difference in levels obtained with a level
C. The earth work in excavation to form the road embankment includes the formation of correct profile and depositing the soil in layers
D. All the above
Answer: Option D
Related Questions on Estimating and Costing
A. Mid-section formula
B. Trapezoidal formula
C. Prismoidal formula
D. All the above
Size, capacity and materials need be specified for
A. Bib-cocks
B. Stop-cocks
C. Ball valves
D. All the above
The expected out turn of 12 mm plastering with cement mortar is
A. 2.5 sq m
B. 4.0 sq m
C. 6.0 sq m
D. 8.0 sq m
A. Excavation
B. Surface dressing
C. Cutting
D. Surface excavation