Pick up the correct statement from the following

A. Programmer evaluation and review technique is event oriented

B. Programmer evaluation and review technique is not event oriented

C. Critical path method is event oriented

D. None of the above

Answer: Option D

Solution(By Examveda Team)

Program evaluation and review technique (PERT) is a technique adopted by organizations to analyze and represent the activity in a project,
and to illustrate the flow of events in a project.
PERT is a method to evaluate and estimate the time required to complete a task within deadlines.

Join The Discussion

Comments ( 7 )

  1. Dr. Akash
    Dr. Akash :
    3 months ago

    None of tha above

  2. Sarveshwer Chandra
    Sarveshwer Chandra :
    4 years ago

    . None of the above

  3. Debashis Das
    Debashis Das :
    5 years ago

    option A is correct.

  4. AMAL NALINAM
    AMAL NALINAM :
    5 years ago

    Option A is righ

  5. Keshav Galav
    Keshav Galav :
    5 years ago

    Option A is right

  6. Keshav Galav
    Keshav Galav :
    5 years ago

    Option A is correct reply me

  7. Keshav Galav
    Keshav Galav :
    5 years ago

    Option A is correct reply me

Related Questions on Industrial Engineering and Production Management