Pick up the correct statement from the following
Answer & Solution
Correct Answer:
Option
D
Program evaluation and review technique (PERT) is a technique adopted by organizations to analyze and represent the activity in a project,
and to illustrate the flow of events in a project.
PERT is a method to evaluate and estimate the time required to complete a task within deadlines.
and to illustrate the flow of events in a project.
PERT is a method to evaluate and estimate the time required to complete a task within deadlines.