Pick up the correct step used for scheduling a project by C.P.M.
Answer & Solution
Correct Answer:
Option
D
For scheduling a project by C.P.M.
- A project is divided into various activities
- Required time for each activity is established
- Sequence of various activities is made according to their importance
- A project is divided into various activities
- Required time for each activity is established
- Sequence of various activities is made according to their importance