Pick up the correct step used for scheduling a project by C.P.M.
A. A project is divided into various activities
B. Required time for each activity is established
C. Sequence of various activities is made according to their importance
D. All of the above
Answer: Option D
Solution(By Examveda Team)
For scheduling a project by C.P.M.- A project is divided into various activities
- Required time for each activity is established
- Sequence of various activities is made according to their importance