Pick up the incorrect statement from the following. A critical ratio scheduling

Answer & Solution
Correct Answer: Option D
critical ratio (CR) is calculated by dividing the time remaining until a job's due date by the total shop time remaining for the job, which is defined as the setup, processing, move, and expected waiting times of all remaining operations, including the operation being scheduled.