Pick up the incorrect statement from the following. A critical ratio scheduling
A. Establishes the relative priorities among various activities on a common basis
B. Determines the status of each activity
C. Adjusts automatically changes in activity progress
D. None of the above
Answer: Option D
Solution(By Examveda Team)
critical ratio (CR) is calculated by dividing the time remaining until a job's due date by the total shop time remaining for the job, which is defined as the setup, processing, move, and expected waiting times of all remaining operations, including the operation being scheduled.Related Questions on Industrial Engineering and Production Management
The essential condition for the decompression of an activity is that
A. The project time should change due to decompression
B. After decompression the time of an activity invariably exceeds its normal time
C. An activity could be decompressed to the maximum extent of its normal time
D. None of the above
A. CAM < DAM
B. CAM > DAM
C. CAM = DAM
D. There is no such criterion