P.M.T.S. (Predetermined Motion Time Systems) include
A. M.T.M. (Method Time Measurement)
B. W.F.S. (Work Factor Systems)
C. B.M.T.S. (Basic Motion Time Study)
D. All of these
Answer: Option D
Solution(By Examveda Team)
A predetermined motion time system (PMTS) is frequently used to perform Labor Minute Costing in order to set piece-rates, wage-rates and/or incentives in labor (labour) oriented industries by quantifying the amount of time required to perform specific tasks under defined conditions.Related Questions on Industrial Engineering and Production Management
The essential condition for the decompression of an activity is that
A. The project time should change due to decompression
B. After decompression the time of an activity invariably exceeds its normal time
C. An activity could be decompressed to the maximum extent of its normal time
D. None of the above
A. CAM < DAM
B. CAM > DAM
C. CAM = DAM
D. There is no such criterion