Routing assists engineers in deciding in advance
A. The flow of material in the plant
B. The methods of proper utilization of manpower
C. The methods of proper utilization of machines
D. The layout of factory facilities
Answer: Option C
Solution(By Examveda Team)
Routing assists engineers in deciding in advance the methods of proper utilization of machines.Related Questions on Industrial Engineering and Production Management
The essential condition for the decompression of an activity is that
A. The project time should change due to decompression
B. After decompression the time of an activity invariably exceeds its normal time
C. An activity could be decompressed to the maximum extent of its normal time
D. None of the above
A. CAM < DAM
B. CAM > DAM
C. CAM = DAM
D. There is no such criterion
Join The Discussion