Routing is essential in the following type of industry
A. Assembly industry
B. Process industry
C. Job order industry
D. Mass production industry
Answer: Option A
A. Assembly industry
B. Process industry
C. Job order industry
D. Mass production industry
Answer: Option A
The essential condition for the decompression of an activity is that
A. The project time should change due to decompression
B. After decompression the time of an activity invariably exceeds its normal time
C. An activity could be decompressed to the maximum extent of its normal time
D. None of the above
A. CAM < DAM
B. CAM > DAM
C. CAM = DAM
D. There is no such criterion