Shyam can complete a task in 12 days by working 10 hours a day. How many hours a day should he work to complete the task in 8 days?
Answer & Solution
Correct Answer:
Option
D
10 × 12 = 8 × x
15 = x
x = 15 days
15 = x
x = 15 days