Shyam can complete a task in 12 days by working 10 hours a day. How many hours a day should he work to complete the task in 8 days?
A. 14
B. 16
C. 12
D. 15
Answer: Option D
Solution(By Examveda Team)
10 × 12 = 8 × x15 = x
x = 15 days