Slack represents the difference between the
A. Latest allowable time and the normal expected time
B. Latest allowable time and the earliest expected time
C. Proposed allowable time and the earliest expected time
D. Normal allowable time and the latest expected time
Answer: Option B
Solution(By Examveda Team)
Slack represents the difference between the Latest allowable time and the earliest expected timeRelated Questions on Industrial Engineering and Production Management