Standard time is equal to
A. (Normal time) - (allowances)
B. (Normal time) + (allowances)
C. Representative time multiplied by rating factor
D. Normal time taken by an operation
Answer: Option B
Solution(By Examveda Team)
Standard time is equal to (Normal time) + (allowances)the standard time is the time required by an average skilled operator, working at a normal pace, to perform a specified task using a prescribed method.
Join The Discussion
Comments ( 1 )
Related Questions on Industrial Engineering and Production Management
The essential condition for the decompression of an activity is that
A. The project time should change due to decompression
B. After decompression the time of an activity invariably exceeds its normal time
C. An activity could be decompressed to the maximum extent of its normal time
D. None of the above
A. CAM < DAM
B. CAM > DAM
C. CAM = DAM
D. There is no such criterion
Standard time = mean average time*rating factor + allowances.
Normal time = mean average time*rating factor.