Standard time is equal to

A. (Normal time) - (allowances)

B. (Normal time) + (allowances)

C. Representative time multiplied by rating factor

D. Normal time taken by an operation

Answer: Option B

Solution(By Examveda Team)

Standard time is equal to (Normal time) + (allowances)
the standard time is the time required by an average skilled operator, working at a normal pace, to perform a specified task using a prescribed method.

Join The Discussion

Comments ( 1 )

  1. Madhavan Palmani
    Madhavan Palmani :
    4 years ago

    Standard time = mean average time*rating factor + allowances.

    Normal time = mean average time*rating factor.