The artificial activity, which indicates that an activity following it cannot be started unless, the preceding activity is complete, is known as
A. Event
B. Free float
C. Artificial
D. Dummy
Answer: Option D
Solution(By Examveda Team)
The artificial activity, which indicates that an activity following it cannot be started unless, the preceding activity is complete, is known as DummyRelated Questions on Industrial Engineering and Production Management